The DEQ on-site sewage page says an Authorization to Construct has to be purchased and issued before a new system is installed or an existing one is modified. After it is purchased, DEQ assigns it to the local environmental specialist for the property. DEQ reviews the Report for On-Site Sewage, the form called the 581, before that authorization may be issued. The 581 decides which system types the property may use, and it describes the minimum dispersal area from the size of the house or the daily flow.
The soil work inside that report is a soil profile when a profile is the test being used. DEQ’s page says a minimum of three holes or pits are dug in the dispersal area so the soil texture can be described. Those results are what decide the allowable types: a conventional subsurface system, aerobic treatment with spray or drip irrigation, or a lagoon. Soil profile tests may be done only by DEQ or a DEQ-certified soil profiler. The live page spells that word “Ceritified.” OAC 252:641-3-1 says a soil test identifies the dispersal site and sizes the field for a new installation, with two exceptions: a lagoon, and an aerobic spray system sized for Group 5 soil in the matching net evaporation zone. A person who writes a soil profile for a design has to be certified by DEQ. DEQ may also do the profile.
A percolation test is a different test. OAC 252:641-3-2 limits it to identifying a dispersal site for a conventional subsurface absorption field. It is not the test that sizes an aerobic spray or drip field. DEQ’s page adds that a perc test may be performed only by someone registered through the Department of Health, and that it is not used in a scenic river corridor or a water body protection area.
Who may install
OAC 252:641-1-2 defines an installer as any person who installs an on-site sewage treatment system, or who contracts to install one or furnishes the labor. A certified installer is narrower: a person in that business whom DEQ has certified to inspect and approve that person’s own installations.
Certification is by category. OAC 252:641-21-1(g) separates them. Conventional, shallow extended, and evapotranspiration/absorption fields share the CSE category. Lagoons are their own category. Aerobic treatment with a spray field is Aerobic-Spray. Aerobic treatment with a drip field is Aerobic-Drip. A certified installer may self-inspect and approve only systems that person installs, and only in a category the person holds. The same rule bars self-inspection of an alternative system and of a small public system with a design flow over 1,500 gallons a day.
One system a year without certification: Effective November 1, 2025, DEQ’s sewage-treatment page says an individual who is not certified through DEQ may install only one on-site sewage treatment system per calendar year. DEQ’s FAQ for that change quotes Title 59, Section 1158, for the certification requirement and says that subsection applies to persons who install more than one individual sewage disposal system per calendar year. The FAQ also says a system installed by someone who is not certified must be inspected by DEQ, the installer must be present, and any deficiency has to be corrected before DEQ issues the final inspection and before the system may be placed into operation.
The sequence to expect
These are the public steps for a new system or a modification. They are not a calendar for how many days a contractor will be on the lot, and they are not a price. The same authorization and inspection steps apply to a lot in Mustang. The mailing-city roster is aerobic septic in Mustang.
Install sequence
- 1
Soil test and the 581The report identifies which systems the lot may use. A soil profile uses at least three holes or pits.
- 2
Authorization to ConstructDEQ reviews the 581, then issues the authorization. A new or modified system waits on that authorization.
- 3
InstallationA certified installer confirms the authorization is issued and tells the local DEQ office the time, date, and location before construction.
- 4
Inspection before useDEQ approves the system, or a certified installer self-inspects it, before the system is placed into operation.
OAC 252:641-1-2.1 says the installer, before installing or modifying a system, obtains either DEQ authorization under the general permit or an individual permit for an alternative system. The application is DEQ Form 641-575, “Request for Authorization/Permit to Construct an On-Site Sewage Treatment System,” with the fee, plus Form 641-581 to the local DEQ office. A design that leaves the rules in the chapter needs the individual permit and Form 641-581Sup.
DEQ’s Certified Installers page tells a certified installer to make sure the authorization has been issued before construction begins, and to notify the local office of the time, date, and location before work starts. OAC 252:641-21-12 states that same notice duty.
OAC 252:641-1-3 says a new installation, modification, or repair is inspected and approved by DEQ, or installed, self-inspected, and approved by a certified installer, before it is backfilled and before it is placed into operation. The sewage-treatment page documents the final inspection on DEQ Form 641-576. When a certified installer completes that inspection, the page says the form is submitted within 15 days. OAC 252:641-21-12 says the completed Form 641-576AS goes to the local office within 15 working days after the work is completed. The Certified Installers page instead says ten working days for Form 641-576AS. Those are three published statements of the filing deadline. This directory does not choose which one an inspector will apply.
State fees for the authorization and for a DEQ soil test are published separately from an installer’s price. See the published state fees, separate from the installer’s price. This page does not add a contractor price.